BIG SPRING, TX — Scenic Mountain Medical Center began a multi-phase parking lot construction project this week. Note that signage and caution tape will guide traffic safely around work areas during this time. Patients & Visitors entering from Martin Luther King Blvd should follow posted signs. The unmarked side of the entryway will remain open. The entire project is expected to be completed on Friday, May 30th.
Phased Construction Timeline:
• Phase 3 (Yellow) & Phase 2 (Red) begin 5/19
• Phase 3 complete by 5/21
• Phase 1 continues, finishes 5/22
• Phase 2 resumes 5/22–5/29
• Canopy area (North side) begins 5/29, finishes 5/30
Expected Completion: Friday, May 30